Relocating services for a new kitchen

What is straightforward, what gets difficult, in which order it happens, and what has to be decided before the wall closes up.

Put your own home to us
Island with a marble top and a sink with a brass tap, facing a tall cabinet wall in dark oak veneer, in a room with herringbone parquet and plastered walls
The short answer

Sockets, light points and water pipes can nearly always be moved. Waste is the hard one: it works by gravity, so your floor build-up decides whether a sink can sit in the island. The extractor duct and the gas line are fixed earliest.

The order is always the same: strip out, services, close up, floor, and only then the kitchen. Anything you change after that costs wall.

This is the part with the most unpleasant surprises, and where thinking ahead pays off most.

The order

Why the drawing comes before the services

PhaseWhat has to be settled by then
Strip outThe new layout in broad terms
Shell workPosition of the extractor and the route of the duct
ServicesEvery appliance, every socket, sink and hob, to the centimetre
Close upEverything. What changes now gets opened again
Screed and floorThe floor thickness, which co-determines the working height
Kitchen installationMeasuring on the finished shell
Connecting and inspectionThe appliances are on site

The most expensive mistake in a kitchen renovation is rarely a choice of material. It is an appliance that moves only after the plastering.

Have your own situation looked at
Electrics

The most movable, with the most rules

Cables do not follow gravity, so this is rarely a technical problem. It is, however, the part with the most regulations.

ApplianceOwn circuitNote
HobJaFused more heavily than a socket circuit
OvenJaConnected load is on the data sheet
DishwasherJaBehind a 30 mA residual current device
Washing machine and tumble dryerJaBehind a 30 mA residual current device
Fridge, extractor, lightingNoMay share a circuit

This follows the AREI, the Belgian general regulation for electrical installations. Cable cross-section and fuse follow from the connected load of the appliance.

A major change or extension requires an inspection by a body approved by the FPS Economy. Two things are forgotten most often: a socket in the cabinet under the sink, and the supply for an island, because that has to run through the floor.

Have your own situation looked at
Water

Supply is the simplest of the five

Water is under pressure and needs no fall, so this is the least work. The points to watch sit elsewhere:

Pale kitchen in polished concrete with a white extractor against the wall above the induction hob, sockets in the back panel, a tall white fridge unit and a sink in the concrete island
Extractor, hob, sockets and sink: four positions that are all fixed before the plastering.
Have your own situation looked at
Waste

The only one that depends on your floor

ComponentGuide figure
Sink waste diameter40 mm is common, 50 mm gives margin
Fallabout 1 to 2 cm per metre
Dishwashermay share the sink waste
Trapsits in the cabinet and costs drawer depth

Work out that fall: four metres to the island is already four to eight centimetres, on top of the pipe itself. If that does not fit, three ways out remain: the island closer to the existing drain, building up the floor, or keeping the sink against the wall.

Black island with a marble top and an induction hob, with the brass sink in the run of units against the wall behind it, bespoke kitchen in Antwerp by Cervano
Black island with brass, Antwerp, 11,290 EUR including VAT and installation. The hob went into the island and the sink stayed against the wall: that meant power through the floor, but no drain. The other projects are listed with their price under projects.
Have your own situation looked at
Extractor

The route out weighs more than the appliance

PointGuide figure
Duct diameter125 mm minimum, 150 mm works better
Bendstwo of 45 degrees beat one of 90 degrees
Reductionnever reduce the diameter along the way
Mounting height above gas650 mm
Mounting height above induction or ceramic550 to 800 mm

Every metre and every bend costs airflow and adds noise. The manual for your extractor states a minimum mounting height of its own; that takes precedence over this table.

If no duct can reach outside, recirculation remains: the smell is filtered, moisture and heat stay indoors. Above an island the duct runs through the ceiling, a decision from the shell stage.

Have your own situation looked at
Gas

The only one you do nothing to yourself

A new gas line or a major change requires an inspection, and without a certificate of conformity the network operator will not open your meter. Have it done by an installer with the CERGA label. Switching to induction removes that, and moves the question to the fuse box.

We draw those connections into the design, so that the services and the cabinets do not collide afterwards. How that goes is on bespoke kitchens in Antwerp. Kitchens we installed that way, with their price, are under the projects.

Your own home

Want to know what can be relocated at your place?

Briefly describe where the connections sit today and where you would want the kitchen. We will tell you which services can move, which become a problem and which decision is best taken first.

A floor plan, a sketch or a few images of the space. Up to six files of 15 MB each.
Your details are used only to answer your question. More in our privacy policy.

Thank you, we have received it.

We will look at your situation and reply within two working days.

Finally

About these rules

Cervano makes and installs the joinery and is not your electrician, gas fitter or inspector; the rules above apply in Belgium as they stood in August 2026, and your installer and the inspection body are the source, not us.

Have your own situation looked at
Further reading

The rest of the knowledge base

Cervano

Rather speak to someone straight away?

Do email us, or leave your details above. The workshop is in Antwerp and you are welcome by appointment.

WorkshopAntwerp, visits by appointment
Emailhello@cervano.be
ReplyWithin two working days